The sale of the Whyalla Steelworks could stretch beyond the end of September, with the South Australian Government saying securing the right long-term owner is more important than meeting an artificial deadline.

Premier Peter Malinauskas provided an update on the future of the steelworks in State Parliament on Tuesday, September 1, saying the government still hoped to identify a successful bidder by September 30, but would not rush one of the most significant industrial decisions facing South Australia.

The end of September had previously been identified as the expected timeframe for the sale to be completed.

However, Mr Malinauskas said the priority for both the State and Federal Governments was ensuring the steelworks had a commercially sustainable future rather than simply completing the transaction by a particular date.

Two companies remain in the race

Australian-owned resources company M Resources and Indian steelmaker Jindal Steel remain the two shortlisted bidders seeking to become Whyalla's next steelworks owner.

The pair were selected from five binding bidders earlier this year, following a process which initially attracted interest from more than 70 parties.

Australian steelmaker BlueScope, which did not make the final two, continues to hold a right of last offer and could potentially re-enter the process if it chooses to match or better the final proposal.

The Federal and South Australian Governments have committed up to $1.9 billion to work alongside the successful new owner to upgrade and transform the ageing steelworks.

The funding is intended to support the transition towards modern, lower-emissions steelmaking while maintaining Australia's sovereign steelmaking capability.

Blast furnace remains a major concern

While negotiations over the future ownership continue, attention also remains firmly fixed on the Whyalla Steelworks blast furnace.

The furnace has been offline since April, with extensive work undertaken in an effort to return it to operation.

Mr Malinauskas told parliament on Tuesday the furnace remained in a precarious condition, although efforts to bring it back online were continuing.

Earlier this year, the government acknowledged hundreds of jobs could potentially be affected if the blast furnace cannot be restarted before the steelworks transitions towards newer steelmaking technology.

Administrators have previously indicated that other parts of the steelworks, including the pellet plant and rolling mills, could continue operating if the blast furnace was ultimately unable to return to service.

Whyalla waiting for certainty

The steelworks has been under administration since February 2025 after the South Australian Government intervened and removed control from Sanjeev Gupta's GFG Alliance following years of financial difficulties and concerns about underinvestment.

Administrator KordaMentha has since operated the facility with substantial financial support from the State and Federal Governments while the search for a new owner has continued.

For Whyalla, the eventual decision will have consequences extending well beyond the steelworks gates.

The facility remains one of the city's most important employers and a significant part of the Upper Spencer Gulf economy, while also producing strategically important Australian-made steel products.

The announcement of M Resources and Jindal Steel as the final two bidders earlier this year provided some long-awaited clarity, but the city is still waiting to learn who will ultimately take control of its steelmaking future.

Tuesday's update means September 30 remains an important target — but no longer appears to be a hard deadline.

For a community which has endured years of uncertainty surrounding the plant, the government says its focus is now on making sure the next owner is capable of delivering a sustainable steel industry in Whyalla for decades to come.